Shipping Guide · Updated November 2026

Durban Port Delays: Why a Throughput Rebound Hasn't Cleared the Queue (Updated November 2026)

In the week ending 1 November 2026, South Africa's container terminals lifted 20% more boxes. That figure comes from Cargo Movement Update No.306, the weekly report compiled by the South African Association of Freight Forwarders (SAAFF) and distributed by Business Unity South Africa (BUSA).

FAQ

Frequently asked questions

Throughput is up 20% — is Durban recovering?

Improving, but not enough to relax. SAAFF's Cargo Movement Update No.306 still puts the average DGT anchorage wait at 266 hours (about 11 days), and the queue rose from 11 ships to 15 on 3 November. The report's own conclusion is that operations have stabilised but have not systematically recovered. Faster discharge is good news; it does not answer when a box gets collected.

Does Maersk's extra day cut my detention bill by a day?

Only if you do exceed free time, and the excess falls on that added day. The 5 days run until 31 December 2026 and revert to 4 on 1 January 2027. The change does not touch demurrage while the box sits in the yard, nor the anchorage wait. Which day the clock starts is set by your bill of lading and the carrier's local tariff.

Which waiting-time figure should I use?

For trend, use the two Kuehne+Nagel 7-day averages. For your own shipment, check the discharge terminal on the bill of lading and ask the carrier for arrival and berthing updates. The 8.3 days is the Transport Minister's 2 October snapshot, the 266 hours is SAAFF's weekly DGT average, and the roughly 12 days appears in one Daily Maverick report only. None of them is a commitment on your booking.

Would switching to Cape Town or Port Elizabeth avoid this?

Some cargo is already moving that way. SAAFF's report shows Cape Town up 76% that week with an average anchorage wait of about 1 hour, and Port Elizabeth up 204%, possibly from diversion out of Durban. But a port change is a separate calculation: delivery point, inland distance and trucking cost all matter. Do not switch just because Durban is congested.

How should I set my delivery window?

Fix the date the goods must be on the shelf, work back through warehouse receipt, inland transport, the truck slot and expected berthing, and leave a buffer of "about 20 days" for the Durban leg. If unsure, send us the shipment date, destination, container type and cargo weight and we will give a conclusion shipment by shipment — you can run the numbers yourself first with the site's ocean freight transit times page.

Worried about a Q4 or January arrival window?

Tell us what you are shipping and where it needs to go. We will come back with a clear rate and a straight answer.